Clever Training will have units for shipping concurrently with 4iiii's, based on pre-order date.
But, they're keeping the Feb date because quite frankly I'm not convinced 4iiii's will ship Dec 10th. I have little doubt they'll hit Jan/Feb, but as I said in my original post back in early September, I think there's just too many little items (mostly non-technical actually) that'll make it extremely difficult to hit that Dec 10th date. Things like consumerization of the calibration kit, packaging design, getting a spot in manufacturing for both the power meter and the kit, as well as testing/validation of final production samples. At present, I haven't seen anything that changes my mind there yet.
Don't get me wrong - I'm actually not as concerned about the technical side - it's just a lot of process and ramp-up that goes into shipping a product into the channel, and I think that's going cause the delays (but, happy to be proved wrong).
-