The slab is for an additon…
They also poured the small sidewalk…
Both are screwed up. I was expecting a smooth finish… but, looks like I’m going to have to settlel for a self-leveling pour over the slab.
…you can’t believe that the contractor poored concrete with rain on the horizon? …Well, believe it… he poured knowing it was going to rain… I come home… it’s done… and started raining cats and dogs a few hrs. later. …total set time was about 7-8 hrs. tops. I called the general contractor and told him what was happening… he was on his way to Houston at the time… and blew some smoke up my ass by saying everything would be OK.
The only options seems to be breaking up the sidewalk portion and starting over. However, the slab portion is going to be tough to breakup… were talking about 8+ inches at one end of slab and about 3+ inches of slab closes to the house (with a 18 inch footing at the outer section of the slab.
Cutting the section that is the worse includes the 8 plus inches thick of slab with 18" footing. We are talking alot of concrete for about 275 sq. ft. (11 yrds.).
Leveler is an option… My question is this… does that stuff last - specially outdoors? As best I can tell, it’s OK for indoors (where temps are relatively constant and freezing doesn’t occur. However, side walks are another matter… Does floor leveler work on side walks in the worse of conditions and over a long period of time - say 15-20 yrs. min.?
We are talking about a 1+ inch leveling pour(s) on large sections of the foundations… and the sidewalk looks like a total mess.
When I looked up the sites about leveling pour products… I see a lot of limitations for depths deeper than 1 inch. And, quite honestly anything over 1/2 inch looks problematic.
Quikrete makes a floor leveler that doesn’t require a latex primer… But, I don’t know if that’s a good idea. Other products use a latex primer then the floor levelor. Hell if I know which will be better… In fact, I wished I had other options but the more I looked at that crappy concrete pour, the more I realized that a skim coating made of a concrete leveler product is the only option.
Cutting the really bad sections (mostly exposed aggregate) sections seems a really tough option since the section that needs to be removed is about 8-10" thick IF you don’t include the 18 inch thick footing (12 inch wide).
FWIW Joe Moya
BTW, the concrete slab will be finished out by laying an extension of a the wood flooring that exists in the adjacent rooms.